Different methods have been used to determine the pile bearing capacity such as static equations, dynamic equations, empirical methods (EMs), numerical methods, computer software programs, and the pile static load test, these methods were giving different values for pile bearing capacity. In this paper, three empirical methods (Ems) have been selected (Brinch-Hansen, Chin-Kondner, and Decourt) and (AllPile 6) software (AP) has been applied to determine the capacity load of piles for six cases study of drilled concrete piles with a diameter ranging from 800 mm to 1500mm and embedded length ranged 10.5m to 26m. Four of those six piles are located at Portsudan city near the red seacoast and two piles are located in Khartoum city. The results of the pile bearing capacity (PC) calculations obtained using the above-mentioned different methods were compared with results produced by the pile load test. In all six cases study, the settlement of piles was limited, settlement failure was not reached. The results show that the AllPile 6 (AP) and the three mentioned empirical methods (Ems) gave reasonable piles bearing capacity, the (AP) and (BHM) gave the better result than the CKM and DM. While (DM) gave results similar to results determined using the (CKM). However, it was not preferred to use the (CKM) and (DM), unless the failure settlement has occurred in the pile load test.
Many studies and researches were conducted on the comparison of different methods for determining piles bearing capacity such as the following. E. Gehan showed a comparison between various prediction methods to obtain the ultimate bearing capacity of the pile, this study compared the measured result of ul-timate pile load capacity for forty-four piles with results obtained using four empirical methods (Brin-ch-Hansen,1963; Chin-Kondner, 1970), Modified (Chin, 1980; Decourt, (1999) and two semi-empiri-cal methods (using correlation with in situ results of SPT and CPT), these data of soil collected from dif-ferent Egyptian soils. The study noted that all emp-irical methods applied gave suitable results, but there are variations in the results with respect to the different methods. In addition, the study concluded that (BHM) and (DM) gave satisfactory results of ul-timate load capacity of piles (Abdelrahman et al., 2003). Eslami et al. (2014) provided a study for deter-mining piles axial capacity based on in-situ tests and static analysis. The results obtained by these methods were more accurate pile s load capacity (Eslami et al., 2014).
Lastiasih et al. introduced some methods for evalu-ating load capacity based on the pile load test. 15 out of 130 pile loading tests reach failure conditions and the remaining cases without reaching failure. In this study, different methods are used to determine pile loading capacity. It was concluded that all methods gave more suitable results and it was recommended to use the method which gives the lower bearing (Last-iasih et al., 2014; Lastiasih and Sari 2020).
Samuel et al. (1999) proposed a method for deter-mining the ultimate bearing capacity of piles from non-failed load tests. Different empirical methods also were used such as Davissons criterion method, Shape of the Curve method, Limited total settlement method, De Beers log-log method, BHM and Chins method. The proposed method and empirical methods were calculated and compared with the measured results of pile load tests (Paikowsky &Tolosko, 1999). In this study, full-scale static and dynamic tests of reinforced concrete cast-in-place piles were proposed for determining the pile loading capacity. The results obtained were more suitable (Kostov & Dikov, 2015). Nonlinear analysis was carried out for deep found-ations subjected to lateral loads to estimate pile load-ing capacity. The values of deflections and bending moments were agreed with field tests (Evans et al., 1994). The prediction of the PC is more useful in foundation design. This study was aimed to propose a soft computing technique to estimate the pile bearing capacity using the Gaussian process regression (Dow-latshahi et al., 2020). Another study was conducted depending on a cone penetration test and piezocone penetration test for evaluating direct axial loading capacity. It was concluded that all tested piles have failed at the end of the static (Hasanzadeh et al., 2013). This study was aimed to apply an artificial neural network model improved with genetic algorithm opti-mization technique to forecast piles loading capacity (Nazir et al., 2014). In this study, different machine learning algorithms including decision tree and perceptron artificial neural network are used to model the pile bearing capacity of cohesion-less soil (Zhou et al., 2020). Another study is conducted to predict single pile loading capacity using in-situ test and prediction methods such as hyperbola, exponent curve, log curve, and gray theory. It is concluded that exponential and hyperbola methods are better than the other method (Iqbal et al., 2020; Zhang et al., 2006).
In this study, different direct and indirect methods such as static and dynamic approaches are used to esti-mate the loading capacity of driven piles if fie grained soil (Abasia et al., 2014). This work is aimed to dete-rmine the bearing capacity of single and pile gro-ups in cohesion-less and cohesive soils (Coyle & Sula-iman 1970). In this work, the discrete method is used to analyze the pile-soil interaction and loading transfer mechanism. Stress and strain distribution in pile-soil interaction in multi-layer soils by using the discrete method (Hong & Mechanics 2002).
Objectives
The paper is aimed to:
1) Determine the pile bearing capacity (PC) by using empirical methods (EMs) and software program (AP).
2) Compare results obtained and to evaluate the variation in the results obtained from different methods and expect to what extend this variation can be effect calculating bearing capacity.
The research method is based on analysis and com-parison of the results for the sample pile bearing cap-acity by applying the EM (Brinch-Hansen, 1963; Chin-Kondner, 1970; Decourt, 1999) and determining the bearing capacity of the same sample pile by using a software program (AP). In this paper, a concrete dri-lled shaft pile was used (Ali, 2018).
Brinch-Hansen method (BHM)
Brinch-Hansen (1963) developed a method which assumed that, the failure is achieved from the assu-mption that hyperbolic relationships exist between the load and settlement. Brinch-Hansen assumption that the shape curve of pile load-settlement is like that, when the settlement (S) are plotted against the square root of settlement divided by the corresponding load ????/???? , the crossing points of and (????/????) plot in straight line having a slope (????1) and a Y-intercept (????2) as shown in Fig 1. Two methods are suggested (80% and 90% criteria), the first method if the load of 80% Qu corresponded the settlement 25% Su and the second method if the load of 90% Qu corresponded the settlement 50% Su, then the pile load capacity (failure) Qu and the settlement at failure Su are determined from following equations:
Qu = 1/ (1)
Su = ????2/ ????1 (2)
Brinch-Hansen considered that the load – settlement curve as shown in Fig 2 is parabolic curve which can determine by using following equation:
Q = ????/(????1S+????2) (3)
Fellenius, (2001) recommended the 80% criterion BrinchHansen, which generally gives a good result to the actual pile load capacity, gained from the static test results.
Chin-Kondner method (CKM)
Chins method, (1970) developed method to piles of the general work by Kondner, (1963), the method was assumed that the hyperbolic relationships exists bet-ween the load and settlement as shown in Fig 5. CKM assumption that the shape curve of pile load settlement
is like that, when the settlement (S) are plotted against the settlement divided by corresponding load (S/Q), the crossing points of (S) and (S/Q) plot in straight line having a slope (????1) and a Y-intercept (????2) as shown in Fig 3. The pile load capacity (failure) (Qu) corresponding to settlement at failure (Su), then the (Qu) and (Su) are determined from following equation:
Qu = 1/????1 (4)
The parabolic curve mentioned above can be deter-mined by using equation:
Q = S/ (????1S+????2) (5)
Where: ????1is the slope of the straight line;
????2 is the Y-intercept of the straight line.
Decourt method (DM)
In 1999 Decourt developed method which assumed that, the method was assumed that the hyperbolic rela-tionships exist between the load and settlement as shown in Fig 6. Decourt assumption that the shape curve of pile load – settlement is like that, when the load (Q) are plotted against the load divided by corre-sponding settlement (Q/S), the crossing points of (Q)and (Q/S) plot in straight line having a slope (????1) and Y-intercept (????2) as shown in Fig 4. The pile load capacity (failure) (Qu) corresponding to settlement at failure (Su), then the (Qu) and (Su) are determined from following equation:
Qu = ????2/????1 (6)
The parabolic curve mentioned above can be dete-rmined by using equation:
Q = ????2????/ (1 − ????1S) (7)
Where: ????1 is the slope of the straight line; ????2 is the Y-intercept of the straight line; Qu is pile load capacity (failure); Su is pile settlement at failure; S is pile settlement corresponding to Q and Q is the applied load
Cases Study
In this section, the different six sites were taken to cal-culate the pile bearing capacity. It will be defined as the following.
All Pile 6 Software (AP)
AP is widely used by engineering companies, cons-ultancies, and agencies in the United States and around the world. AP is a windows-based analysis program, which analyzes all types of piles and shallow foun-dations. The AP consists of six main windows for in-putting data and two main windows for outputting results. The following steps describe using the AP software:
a. The first window (Pile Type) contains information about the pile type, the project title, and units (Eng-lish or Metric).
b. The second window (Pile Profile) includes infor-mation about the Pile such as length (L), Top height (H) above N.G.L, and surface angle (As), batter angle (Ab).
c. The third window (Pile Properties) contains in-formation about pile properties such as depth from pile top to beginning of each section, the pile shape and material, pile outside condition, pile inside material, pile diameter variation, % in-side material in total area (At), in addition to the calculator.
d. The fourth window (Load and Group) contains information about the number of piles (single pile, group piles, tower foundation), types of loading on the pile and % load supported by pile cap.
e. The fifth window (Soil properties) comprised inf-ormation about soil profile such as distance from the ground to beginning each layer, depth of gro-undwater, surface elevation (optional input), the soil type, and number of SPT.
f. The sixth window (Advanced page) contains information related to analysis as the zone of zero friction, zone of negative friction, analysis para-meters, and settlement calculation method (Vesic method or Rees method).
g. By the end of step six, all input data will be com-pleted and the program has ready to give output results. The program has the ability to give the results in two options Vertical analysis results or Lateral analysis results; also it can prepare sum-mary reports.
Site (A)
Portsudan housing towers project, tower No.8, site (A) is found in Portsudan city on the coast of the Red Sea. One drilled concrete pile without a case is tested, with a diameter of 1000 mm and embedded length of 30 m, the static load test was done by the ESD Company. The site (A) investigation and test results generally indicated a relatively deep top layer of alluvial deposits that are underlain by completely weathered limestone. Groundwater was measured at 0.68m to 1.28m depth below the ground surface. The SPT test results indi-cated very loose to very dense. The geotechnical rep-ort is established in laboratory and field tests made on five boreholes with deep of 40 m carried by an engine-eering service and design (ESD) company, it is the famous consultancy companies in geotechnical engine-eering in Sudan.
Site (B)
Portsudan towers project, tower No.7, site (B) is situated in Portsudan city on the coast of the Red Sea. Boarded concrete pile without a case has diameter of 100 mm and embedded length of 24 m is tested. The static load test was done by the ESD Company. The site (B) investigation and test results generally indi-cated a deep top layer of alluvial deposits that are underlain by completely weathered limestone. Grou-ndwater at about one meter depth below ground surface. The SPT test results indicated very loose to very dense. The geotechnical report is constructed by laboratory and field tests made on five boreholes with deep of 30m, carried out by the engineering service and design (ESD) company.
Site (C)
Portsudan new depots (LPG), site (C) is positioned near Portsudan city on the coast of the Red Sea. Drilled concrete pile without a case has diameter 1500 mm and embedded length of 10.5 meters is tested, the load test was done by ESD Company. The site C investigation and test results generally indicated completely to moderately weathered coral reef lime-stone that contains marine shells and fossils. Groun-dwater at about three-meter depth below ground surface. The SPT test results indicated moderate to very dense. The geotechnical report is created by lab-oratory and field tests made on seven boreholes with deep of 15m to 20 m, carried out by an engineering service and design (ESD) company.
Site (D)
Portsudan new power plant project, site (D) is located near Portsudan city on the coast of the Red Sea. Drilled concrete pile without a case has diameter 800 mm and embedded length of 16 m is tested, the load test was done by ESD Company. The site D invest-igation and test results generally indicated completely too moderately weathered coral reef limestone that contains marine shells and fossils. Groundwater at about three-meter depth below ground surface. The SPT test results indicated moderate to very dense. The geotechnical report is established by laboratory and field tests made on 20 boreholes with deep of 20m to 30 m, carried out by (ESD) company.
Site (E), pile P-1 and pile P-2:
Altadamon Islamic bank, a new tower (22 floors) located in Khartoum city Almogran. Two drilled concrete piles have a diameter of 1200 mm and emb-edment lengths of 25.5 m and 26m were tested, the groundwater at about four-meter depth below ground surface. The surrounding soil contains alluvial clay, alluvial sand, silty sand, mudstone, and sandstone with quartz pebbles. The SPT test results indicated medium dense to very dense. The summary of cases studies was presented in Table 1.
The results were obtained by application of (AP) and referring to soil data of selected sites and by app-lication of EMs (Brinch-Hansen, Chin- Kondner and Decourt) which has been explained in section 3 were illustrated in Tables (2-8). In all cases, the applied settlement of the piles was restricted, settlement failure was not attained. The results were summarized as follows:
a) The average factor of safety of pile load cap-acity is 4.5 with a standard deviation is 2.56, which appeared in Brinch- Hansen method as presented in Table 3.
b) The minimum value of factor of safety of pile load capacity is 1.4 which appeared in the (DM), as illustrated in Table 3.
The (AP) and (BHM) gave better results in comparison to the other two methods. Comparison of results between ultimate load capacity determined by (AP) and results obtained using EMs as shown in Table 4. Comparison of the results between pile load capacity at constant settlement obtained by using (AP) software and stated (EM) with results of pile load test was shown in Tables 7-8.
Table 1: Cases studies data summary.
All the mentioned methods stated in the paper (AP and the mentioned EMs) determined the satisfactory PC, but there is variation in piles factor of safety. The dis-cussion of results was summarized as follows:
1) It was noticed that, for the piles load test, the settlement corresponding 1.5 working load is very small, (less than 3.5 mm) as illustrated in Table 6, and the vertical load – settlement curves did not achieve failure settlement, for that it is much difficult to determine the actual PC.
2) In comparison with the small values of settlement corresponding to the large values of loads, it was found that the AP and the BHM gave the best-predicted PC results as shown in Table 2.
3) It is difficult to make comparisons of PC obtained using the EMs and AP program because the vertical load – settlement curves did not achieve failure settlement. For the previews reason, a method for the comparison is suggested to take constant settlement corresponding to the different PC obtained using each method as shown in Table 5-6.
4) In the suggested method, it was observed that BHM, CKM, and DM gave results slightly differ-ent from measured results at load test with a mar-gin of about 12%, 9%, and 11% respectively as shown in Table 7–8. The AP gave results totally different from obtained results from the load.
5) DM gave results of pile load capacity similar to those results determined using the CKM with the factor of safety about 2.5 for working load, it was found that both two methods underestimated results.
6) It was found that results obtained using AP under-estimate the PC as illustrated in Table 5 - 6.
The conclusion was drawn as follows: In all samples of the study, the vertical load – settlement curves did not achieve failure settlement, so it is much difficult to know the true ultimate bearing capacity of piles. The BHM and AP gave the best results of the ultimate PC. Comparison of the results of pile bearing capacity using the different EM with that results obtained from load pile tests at constant settlement, it found that BHM, CKM, and DM gave results slightly different from results obtained by load test with a margin about 12%, 9%, and 11% respectively, while the AP pro-gram gave results totally different from measured results of load test as shown in Table 7-8. The adv-antage of CKM and DM is that it was fast to draw the curve of vertical load-settlement during the pile load test in progress.
Recommendations were summarized as follows:
1) It was recommended to use (AP), to determine the PC for the reason that, it gave satisfactory results, in addition, that it gave simple and economical design.
2) In addition to using the computer software pro-gram, the BHM may use for quality control assurance depending on the size and condition of the project.
3) Further researches are required by using different empirical and computer software methods taken into consideration the whole variables affecting the pile load capacity such as soil types, pile dimensions, materials, and construction methods, a large number of samples should be considered in those researches.
We are so much acknowledged to Prof. Dr. Tayeb Hassan Onsa for his guidance to this research.
The authors declare that they have no competing interests with respect to the research.
Academic Editor
Dr. Toansakul Tony Santiboon, Professor, Curtin University of Technology, Bentley, Australia.
Assistant Professor, Dept. of Civil Engineering and Faculty of Engineering, Albaha University, Aqiq, Kingdom Saudi Arabia.
Yousif AAA., and Ali EHM. (2021). Determination of piles bearing capacity using empirical methods and (AllPile 6) software -cases studies Portsudan and Khartoum cities, Int. J. Mat. Math. Sci., 3(5), 113-121. https://doi.org/10.34104/ijmms.021.01130121